Los Angeles Museum of Art (LACMA) Renzo Piano Workshop

JD2 was brought on board as the construction manager for the steel package. We procured early mill rolls of steel at a minimal management fee prior to the design being completed, which allowed our client to reduce the schedule substantially without locking into a particular fabricator too early. Once the design was complete, the steel was ready to ship to the fabricator. This saved our client time and money. We also helped to work out difficult design challenges in the pipe roof trusses, which could be visible through the glass roof, and ultimately saved our client a substantial amount of money.
Matt Constructions LA County 400,000